We’ll tell you what types of work the builders of the business class residential complex “Crystal Avenue” in Petropavlivska Borshchahivka are currently involved in.
In the second phase (11-A, Oksamytova St.) facade, finishing works and installation of elevators proceed. Installation of apartment and vestibule doors (3-14 floors) proceeds.
In the third phase (1-A, Kryshtaleva St.) improvement of the adjacent territory (laying of paving slabs and installation of a playground) proceeds.
In the fourth phase (1, Kryshtaleva St.) window frames have been installed on the 17th floor. Plastering works are underway on 8-9 floors. Heating installation has been started (3-4 floors are ready).
In the fifth phase (1 – B, Kryshtaleva St.) the floor slab of the second floor is being prepared.