The up-to-date report from the construction site of the residential complex "Shchaslyvyi" (Lviv) in Bihova Street.
The following works have been completed:
•installation of apartment doors (2-17 floors);
•tiling the floor in pubic usage places (10-11 floors);
•preparatory work for the installation of the suspended ceiling "Armstrong";
•welding of gas pipeline pipes around the perimeter of the house (60% ready).
Among the following planned stages of work:
•sprinkling sand around the house to the level of the bottom of the landscaping pie;
•decoration of public usage places (plastering of walls on 4-7 floors; tiling of floors on 8-9 floors; application of decorative plaster on 8-9 floors);
•installation of the "Armstrong" subsystem (14-17 floors);
•building internal fire networks;
•installation of office and kindergarten doors on the 1st floor;
•installation of inspection hatches of water niches and weak points;
•installation of a passenger elevator;
•completion of installation of the gas pipeline around the house;
•the beginning of installation of gas meters in apartments.